June Update: One Tropica Fulfilling Homeowners’ Expectations on Quality and Perfection
– Interior fit-out of 172 sold-out units (40% of total) to be completed in November 2024.
– Exterior plastering finished for 300 units (70% completion).
Interior plastering finished for 380 units (90% completion).
– Secondary structure of Queen Villa, Single Villa, and Twin Villa: false ceiling keel, LV, and ELV cabling completed.
– Exterior painting finished for 268 units (63% completion).
– Roof waterproofing, including protection coating, completed for 230 units (including showrooms), 55% completion.
– Exterior aluminum window installation completed for 297 units (70% completion).
– We spare no effort in achieving a timely handover!